The system has triggered more than 3 G100 compliance violations (export or import limit exceeded) in a 30-day period and has been locked out.

Incorrectly set export limit in Enphase appGrid profile not set correctly for DNO requirementsHigh import events from heat pump or EV charger tripping import limit
STEP 1
This lockout can only be cleared by Enphase Support — call +44 1908 828 928. Do not attempt to power cycle to clear, this will not work
STEP 2
After lockout is cleared, review and correct G100 export and import limit settings in the Enphase app. Ensure limits match the DNO approval
Always escalate G100 lockout — requires Enphase Support to unlock remotely. Up to 3 self-clearing violations per 30 days are permitted before lockout
Need full interactive diagnosis?
Faultpath walks you through decision trees, fault codes, and commissioning — built for solar & battery engineers.
Open Faultpath

More Enphase fault codes

ACVOOR
AC Voltage Out of Range
ACFOOR
AC Frequency Out of Range
DC Res Low
DC Resistance Low (Ground Fault / GFDI)
DC Too Low
DC Input Voltage Too Low
DC Too High
DC Input Voltage Too High